21 December 2010
30 November 2010
Shed a little light
18 November 2010
14 November 2010
Look Mom, no scaffolding!
12 November 2010
What a week!
08 November 2010
02 November 2010
and the facade goes on
As the cement board is fastened the scaffolding is coming down exposing the finished facade.
27 October 2010
Here's the skin-ny
16 October 2010
15 October 2010
Blocking for the Stair
29 September 2010
frame it
Window prep work has been completed. Two pieces of wood blocking have been attached to the block walls on the sides and top, and a slate sill has been installed on the bottom. All window openings were measured three times and we are currently waiting for a sample window to be delivered to the site, to verify the depth and sill. Then the window production will begin.
15 September 2010
Coping
06 September 2010
The roof, the roof, the roof is on.....
The roof consists of a series of layers on top of the plywood decking. First, the plywood decking was vacuumed and mopped, before the firestone self adhesive underlayment was placed. The next layer is sheets of 2" rigid insulation that are attached with 3" epoxy coated screws with large galvanized washers. Cant strips were placed in the intersection of the roof and parapet walls. Another layer of the firestone self adhesive underlayment, was applied. The top layer is a firestone rubberized cold application roof with a white granular finish. The remaining exposed parapet will be parged on the interior side.
30 August 2010
Bulkhead
22 August 2010
All Block Done
Done!! The mason finally finished all the block! It was a long time, fill with weather, building department issues, and coordination of the other trades. Here it is....