22 August 2010

All Block Done

Done!! The mason finally finished all the block! It was a long time, fill with weather, building department issues, and coordination of the other trades. Here it is....

This is the low party wall separating the two buildings on the roof.




The tall portion in the back will be the stair bulkhead.






The bulkhead will have two exterior sides of block and the interior sides will be framed with metal studs. The masonry is prepped to receive the joists.
The roof is pitched to the rear of the house, where the roof drain is. (Like the tennis bubble?)Next is framing the rest of the bulkheads, setting the coping stones, and then the final roof.