The sidewalk shed was removed on Monday and now there is so much more light on the 1st floor. This is especially good with the short gray days.
30 November 2010
18 November 2010
14 November 2010
Look Mom, no scaffolding!
12 November 2010
What a week!
Plumbers ran the tubing for the radiant floor heating.
The framers followed framing the 3rd and 4th floors of 103 Boerum Place. I had marked all the walls and door openings with blue masking tape ahead of time, so that they had lines to follow.
This is the bathroom door and walk-in closet door standinge in the Master Bedroom. I had also marked all the electrical outlets so that John & I could attach the boxes. The electricians will come once all the walls are framed. 

The plumbers also attached all the rough-ins for the wall mounted toilets on the 3rd and 4th floors.
While all this was happening inside, the sun was shining and the masons were continuing the cement fiber board. The scaffolding is down and only the sidewalk shed is left. I will post an image of that this weekend.
08 November 2010
02 November 2010
and the facade goes on
The cement board has many steps. The first step is putting a liquid primer on the masonry blocks - as seen in this photo.
As the cement board is fastened the scaffolding is coming down exposing the finished facade.

The second step is adhering the Grace Product Perm-A-Barrier to the block. While this is being done the treated lumber that frames the window openings is being capped with a matte black metal capping. We worked with a local metal fabricator to get the exact profiles that would fit over the wood.
As the cement board is fastened the scaffolding is coming down exposing the finished facade.
27 October 2010
Here's the skin-ny
The masonry brickwork is complete. The remaining material is the cementboard. There are a few steps that need to be done before we can attach the cementboard. The concrete blocks must first be sealed with a liquid primer. This ensures that the surface is dust free so that the perma-barrier (the black material) can adhere to the concrete block. Metal furring strips are anchored and caulked. Metal furring strips receive a rubber gasket that is sandwiched between the exterior fiber cembentboard and metal furring. The cementboard is predrilled and fastened with stainless steel screws with matching colored heads. Hopefully the weather holds up.