Bulkhead

Now that we have had some beautiful (and hot) weather, the bulkheads are really taking shape. The bulkhead is the enclosure for the stair as it continues up to the roof. The two exterior sides are block, while the two interior wall are heavy gauge steel studs, with exterior grade plywood. It will get a finished layer of cement board, but not until the roofing is complete.







22 August 2010

All Block Done

Done!! The mason finally finished all the block! It was a long time, fill with weather, building department issues, and coordination of the other trades. Here it is....

This is the low party wall separating the two buildings on the roof.




The tall portion in the back will be the stair bulkhead.






The bulkhead will have two exterior sides of block and the interior sides will be framed with metal studs. The masonry is prepped to receive the joists.
The roof is pitched to the rear of the house, where the roof drain is. (Like the tennis bubble?)Next is framing the rest of the bulkheads, setting the coping stones, and then the final roof.











19 August 2010

Up on the Rooftop

The masons are on the roof, putting the last of the blocks on the parapets and bulkhead. The bank inspector was there today, so we went up to the roof to document the amount of work completed. I am loving the territorial views - no major landmarks, but we can see a few buildings in lower Manhattan, along with beautiful downtown Brooklyn.

















18 August 2010

Slab in the Cellar


We had a Saturday permit, and we were able to finally pour the slab in both of the cellars. It finally is a clean smooth space with lights. I can't wait to have it house all the toys, games, and kids stuff (at least in our house).

Oh, it will also be very warm, as they poured the concrete over the radiant heat tubes.

11 August 2010

Shed over Head




With the house nearing 40' we are required by the Building Department to provide overhead protection. G + M came out and within 2 hour put up the sidewalk shed. This gives us much more shade in the front of the building and a covered walkway for the pedestrians. Masons are there working this week.


05 August 2010

Water Connection & Radiant Tubing





It is amazing to see how the water will be entering the buildings. The connection is a 3" water line. This is larger than most houses, as we will also have sprinklers throughout our house. Also, while work is happening in the street, the tubing for the radiant floor in the cellar was placed. It looks so straight and organized, but will all be encased in concrete soon.


03 August 2010

Water, Sewer and Rebar - oh my



The water and sewer lines have been connected from the street (last post) through the foundation wall, into the house. While this was going on, there was work done inside as well. The pump was installed in the Cellar - and then rebar was installed for the concrete slab.