After almost 20 months, the construction fence is gone. The sidewalk and curb was poured and the fence was removed. The entire building can now be seen. It is incredible to finally see the both of the buildings.
30 March 2011
21 February 2011
the day the temperature reached 60
The temperature reached 60 degrees last week, and everyone had something outisde to work on. The plumbers and HVAC crews had work on the roof - the vent pipes and the ductwork that connects the inside ducts to the rooftop unit. The electricians ran conduit up to the roof and to the front and rear yards. Exterior lights arrived the same day and were installed. Our crew dug a trench and buried a pipe in the rear yard to connect the phone and cable lines - so that we would not have lines running overhead.
foaming at the wall
orange you glad
do you want a piece of me?
06 January 2011
Back door Slider
01 January 2011