25 June 2011

And then there was One (O-One)

During the last 20 months, we have been working on two buildings. We finally finished 103 and the new owners moved in almost three weeks ago. There was a lot of little punchlist items that needed to be taken care of and lots of paperwork at the building department along with inspections. Here are a few images of the final product.






Come on baby light my fire


We had a opening framed in the shaft that runs through the house that houses all the ducts, piping, and wiring to accomodate the fireplace. After much research we decided on the Napolean Modern 46" gas fireplace. We loved the look of this type of fireplace. We connected the electrical ignition and ductwork and then furred the face of the opening. The surround must be a non-combustable material. We used fire rated gwb covered in cement board that was reclaimed from the front facade.







BPP - Builders Pavement Plan



As part of a new house, the sidewalk and the street directly in front of the new building must also be rebuilt. We have had to dig up the street and sidewalk various times during construction for foundation, electrical, gas, water and sewer work. All of which has disturbed the sidewalk and street frontage. The BPP is an application with the Building Department that requires drawings, surveys, elevations and details of the sidewalk construction and street pavement. It also requires coordination with the Department of Transportation (fees and permits). I

In new construction you are also required to provide street trees in front of the property. I had spent hours going through the list of botanical names of the allowable trees looking for the perfect type. When the Parks Department came to verify my street tree location, to my dismay, there was not enough room for a new tree in front of each building. There are certain requirements that must be met. (minimum distances from gas, electrical or water lines) So we were required to pay into the street tree fund ($1900 per tree) and two trees were planted in our neighborhood.

The major part of the sidewalk work happened when I was in Moorhead, MN for Grandpa Louies 90th birthday. They poured the sidewalk. It was a lot of work and when the final survey was done - the elevations were only off by 3/100" - perfect by concrete pouring standards.

The final portion was quick, but needed to be coordinated with alternative sides parking. Once a week there is no parking on our side of the street on Tuesdays from 8:30-10 so that the street can be swept. We needed to wait until a Tuesday to do the street paving work. Our biggest problem was that three Tuesdays in a row alternative sides was not in effect due to religious holidays (mainly Easter).

The inspection went flawless and here is our lovely sidewalk and street frontage.

Stepping up

So the stairs turn out to be a large design element in the space. The stair is located in the back corner of each building and has 69 risers from the cellar to the roof. The stairs were fabricated out of steel with a monostringer (one support down the middle). The steel is extremely heavy and thick. There is a landing between each floor with a large window. The stairs are quite open and there is a lot of light that comes from the various floors.




The monostringers are bolted to the large triple wood members as they meet the floor joists and at the landings. Steel plates were then weleded to the monostringers to create steps (treads). Railings were then welded to the steel plates and to posts at each landing and floor. The entire steel stair structure was painted. I was leaning towards high gloss white - but with the super white walls and ceilings, we opted for grey. Finally 1-1/2" oak treads were attached to the steel plates (the metal fabricator prepped the steel plates with predrilled holes) - for the final result.